Our projects

Contracting works at Rim Natural Mineral Water S.A.L. bottling site in Kaa El Rim, Zahle - Lebanon Project
  • The project consists of road excavation works, retaining walls, fair faced reinforced concrete rooms, side walks, rain water channels curbstones, interlock pavement, asphalt works, street lighting works and all infrastructure works including electrical, waste, water and rainwater networks.

Client: Rim Natural Mineral Water S.A.L.

Contract Duration: 15/08/2022 - 10/01/2024

Spinneys Supermarket Zahleh Houch EL Oumara
  • The project consists of excavation of 4681.4 m2 area, filter fill, subbase and base course works.

Client: GMRL s.a.l.

Address: Dbayyeh, Beirut, Lebanon.

Bekaa Hospital
  • The project consists of excavation of 2800 m2 area, subbase and base course works. Construction of reinforced concrete basement and ground floor of area 2500m2 each and four floor of area 1080m2 each.

Client: Bekaa Hospital

Address: Taalabaya, Sanewber str., Beqaa, Lebanon.